Spring Field Review Site 03 2017HaywoodClyde Bridge on I-40 Eastbound over Hyder Mountain Road

Issue

Material appeared to be performing well. Contractor expressed concern with how fast the material set-up during placement and the amount of labor required to place the material

Action Item

Structures Management and Construction will review the materials placement and performance and discuss future uses.

Issue

Discussions of using the product as a patch material on concrete decks.

Action Item

Structures Management and Construction will investigate the products potential use as a patch material for concrete bridge decks.

Issue

24 Hour Latex Overlay used did not achieve the required strength within the allowable time specified in the contract. Required strength was eventually achieved.

Action Item

Structures Management will investigate the issue and possible solutions.

Bridge preservation project utilizing Phoscrete product for joint nosing in lieu of elastomeric concrete.