| | under review | aluminum headwalls with deadman anchor design for 48-inch diameter pipe culvert | Robeson | | 4/28/2015 | 5/7/2015 |
| | Accepted, See Email | overhead sign support designs -1 assembly - metalwork and foundations | Wayne-Lenoir | | 4/24/2015 | 5/4/2015 |
| | Accepted | sound barrier wall No. 3 - steel column fabrication & erection details - 134 columns | Guilford, Rockingham | | 4/14/2015 | 4/22/2015 |
| | Accepted | sound barrier wall No. 3 - reinforcing details for steel post anchorage - Revision of Apr 08 | Guilford, Rockingham | | 4/9/2015 | 4/28/2015 |
| | Superseded by April 09 submittal | sound barrier wall No. 3 - reinforcing details for steel post anchorage - Revision of Apr 07 | Guilford, Rockingham | | 4/8/2015 | 5/4/2015 |
| | under review | materials approval: neoprene sealant for deck expansion joints | Brunswick | 5/5/2015 | 5/5/2015 | 5/14/2015 |
| | under review | reinforcing plan for cast-in-place concrete facing for SMSE walls | Caldwell, Watauga | 5/12/2015 | 5/12/2015 | |
| | under review | motor and brake assembly | Pasquotank & Camden | 5/11/2015 | 5/11/2015 | |
| | Accepted as Noted | bridge electrical functional test procedure; eastbound only | Pasquotank & Camden | 4/22/2015 | 4/22/2015 | 5/4/2015 |
| | under review | two-line tubular aluminum handrail at traffic gates | Pasquotank & Camden | 4/10/2015 | 4/14/2015 | 5/13/2015 |
| | Revise and Resubmit | hydrodemolition water management plan | Pasquotank & Camden | 4/3/2015 | 4/3/2015 | 4/14/2015 |
| | Accepted | shotcrete & epoxy injection materials | Hertford / Gates | | 4/20/2015 | 4/22/2015 |
| | Handled w/ Nov. 4, 2014 submittal | proposal to place latex mobile mixer trucks on bridge deck | Cumberland | | 4/27/2015 | 4/27/2015 |
| | under review | deck closed drainage system - review of concrete insert spacing only | Carteret | 4/29/2015 | 4/30/2015 | 5/11/2015 |
| | Accepted as Noted | falsework & formwork design for pier caps - Bents 1 to 10 - Part I, II & III | Carteret | | 4/7/2015 | 4/10/2015 |
| | Accepted as Noted, See Email | prestressed concrete deck panel design - 26 spans - Revision of Mar 31 | Carteret | 3/31/2015 | 3/31/2015 | 4/13/2015 |
| | Accepted, See Email | falsework & formwork design for pier columns (stems) - Bents 11 to 13 - Part I & II | Carteret | 3/30/2015 | 3/31/2015 | |
| | Accepted | cover plates for expansion joints at median barrier - 8 assemblies | Cumberland | 4/24/2015 | 4/24/2015 | |
| | Acceptable | proposal to travel across stage I & stage II of new bridge, and old existing WBL bridge, with two rough terrain cranes | Buncombe | 5/11/2015 | 5/11/2015 | |
| | submittal withdrawn by contractor | proposal to travel across stage one of new bridge with rough terrain crane | Buncombe | | 4/2/2015 | 4/29/2015 |
| | Accepted As Noted | overhead sign support assembly designs - 11 assemblies | Forsyth | 4/9/2015 | 4/10/2015 | 5/5/2015 |
| | under review | fabricated metal stay-in-place deck forms for two prestressed girder bridges | Pender & Brunswick | 5/11/2015 | 5/11/2015 | |
| | Approved, See Email | Type III prestressed concrete girders - 8 members | Pender & Brunswick | 4/1/2015 | 4/1/2015 | 4/9/2015 |
| | Accepted | intermediate diaphragms - 6 steel channel assemblies - Revision of Mar 30 | Pender & Brunswick | | 3/30/2015 | 4/27/2015 |
| | Accepted | one-line elliptical aluminum rail system - 385 linear feet - Revision of Apr 29 | Chatham, Randolph, Mo… | 4/30/2015 | 4/30/2015 | 5/5/2015 |
| | Accepted | standard one-line elliptical aluminum rail system - 385 linear feet | Chatham, Randolph, Mo… | 4/14/2015 | 4/14/2015 | 4/13/2015 |
| | under review | temporary shoring design - soil nail wall for three-sided culvert construction | Ashe, Avery, Wilkes, W.. | 5/13/2015 | 5/13/2015 | 5/13/2015 |
| | Comments sent to Jon Almond | temporary shoring design - soil nail walls at end bents - Revision of Apr 30 | Ashe, Avery, Wilkes, W.. | 4/30/2015 | 5/3/2015 | |
| | handled by Geotechnical Engineering Unit | temporary shoring design - soil nail walls at end bents | Ashe, Avery, Wilkes, W.. | 4/16/2015 | 4/16/2015 | 4/16/2015 |
| | under review | timber temporary structure - addendum | Aleghany, Wilkes, Avery, | | 4/27/2015 | |