2012 Standard Provisions

 
  
  
  
  
  
SP01 G001.docx
  
SP01GPROJECT SPECIAL PROVISIONS - General1995-07
SP01 G003A.docx
  
SP01GNOTICE TO BIDDERS (2 Cluster Projects)2014-01
SP01 G003B.docx
  
SP01GNOTICE TO BIDDERS (3 Cluster Projects)2014-01
SP01 G004.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (With Permits)2007-12
SP01 G005A.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Float, With Permits)2007-12
SP01 G005B.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Float, No Permits)2007-12
SP01 G007A.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Reforestation, With Permits)2007-12
SP01 G007B.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Float, Reforestation, With Permits)2007-12
SP01 G007C.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Reforestation, No Permits)2012-04
SP01 G007D.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Float, Reforestation, No Permit)2012-11
SP01 G010A.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (No Permits)2007-12
SP01 G010B.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (Signals, No Permits)2007-12
SP01 G013A.docx
  
SP01GINTERMEDIATE CONTRACT TIME # 1 AND LIQ. DAMAGES (Reforestation)2012-02
SP01 G013B.docx
  
SP01GCONTRACT TIME AND LIQUIDATED DAMAGES (No Permits)2007-12
SP01 G014A.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Combined)2007-02
SP01 G014B.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Holiday Lane Closure)2007-02
SP01 G014C.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Lane Closure, Time Restricted)2007-02
SP01 G014D.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Road Closure Hour)2007-02
SP01 G014E.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Road Closure Minute)2013-10
SP01 G014F.docx
  
SP01GINTERMEDIATE CONTRACT TIMES FROM___TO___2013-06
SP01 G014G.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Consecutive Hours)2013-06
SP01 G014H.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Consecutive Days)2013-06
SP01 G014I.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Inductive Loop Installations)2013-05
SP01 G014K.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Dates, Maps)2013-06
SP01 G014L.docx
  
SP01GINTERMEDIATE CONTRACT TIMES (Dates, TMP)2013-06
SP01 G015R.docx
  
SP01GPROSECUTION OF WORK (Multiple Maps)2012-08
SP01 G016.docx
  
SP01GPERMANENT VEGETATION ESTABLISHMENT2013-10
SP01 G017R.docx
  
SP01GRAILROAD GRADE CROSSING (Not on Interstates)2013-01
SP01 G022A.docx
  
SP01GDELAY IN RIGHT OF ENTRY1995-07
SP01 G022B.docx
  
SP01GDELAY IN RIGHT OF ENTRY (Multiple Dates)1995-07
SP01 G024R.docx
  
SP01GPOSTED WEIGHT LIMITS2012-08
SP01 G025.docx
  
SP01GPROGRESS SCHEDULE (RAIL)2013-02
SP01 G028.docx
  
SP01GMAJOR CONTRACT ITEMS2002-02
SP01 G031.docx
  
SP01GNO MAJOR CONTRACT ITEMS2007-08
SP01 G034.docx
  
SP01GNO SPECIALTY ITEMS1995-07
SP01 G037.docx
  
SP01GSPECIALTY ITEMS2012-01
SP01 G040.docx
  
SP01GSPECIAL REQUIREMENTS FOR WORK IN NATIONAL FOREST1995-07
SP01 G043.docx
  
SP01GFUEL PRICE ADJUSTMENT2014-02
SP01 G057.docx
  
SP01GPAYOUT SCHEDULE2012-01
SP01 G058.docx
  
SP01GSCHEDULE OF ESTIMATED COMPLETION PROGRESS2014-05
SP01 G061.docx
  
SP01GDISADVANTAGED BUSINESS ENTERPRISES (Central Let)2013-12
SP01 G062.docx
  
SP01GDISADVANTAGED BUSINESS ENTERPRISES (Division)2013-12
SP01 G063.docx
  
SP01GDISADVANTAGED BUSINESS ENTERPRISES (Local Government Agency)2013-12
SP01 G064.docx
  
SP01GDISADVANTAGED BUSINESS ENTERPRISE (Rail)2013-05
SP01 G066.docx
  
SP01GMINORITY AND WOMEN BUSINESSES (Central Let)2013-12
SP01 G067.docx
  
SP01GMINORITY AND WOMEN BUSINESSES (Division)2013-12
SP01 G068.docx
  
SP01GMINORITY AND WOMEN BUSINESSES (Local Government Agency)2013-12
SP01 G070.docx
  
SP01GARRA AND OERI CONTRACT PROVISIONS AND REPORTING REQUIREMENT CERTIFICATION2013-05
SP01 G071.docx
  
SP01GSPECIAL NOTICE TO BIDDERS2013-10
SP01 G072.docx
  
SP01GPREQUALIFICATION OF RAIL ROAD GRADING CONTRACTORS (PIP)2013-02
SP01 G073.docx
  
SP01GPROTECTION OF RAILROAD INTEREST2013-10
SP01 G085.docx
  
SP01GCERTIFICATION FOR FEDERAL-AID CONTRACTS1990-03
SP01 G088.docx
  
SP01GCONTRACTOR'S LICENSE REQUIREMENTS1995-07
SP01 G100.docx
  
SP01GU.S. DEPARTMENT OF TRANSPORTATION HOTLINE (Federal Aid Projects)1994-11
SP01 G103.docx
  
SP01GSUBMISSION OF RECORDS (Federal Aid BRZ Projects)2012-08
SP01 G112A.docx
  
SP01GSUBSURFACE INFORMATION (Information Not Available)1995-07
SP01 G112B.docx
  
SP01GSUBSURFACE INFORMATION (Roadway only)1995-07
SP01 G112C.docx
  
SP01GSUBSURFACE INFORMATION (Structures only)1995-07
SP01 G112D.docx
  
SP01GSUBSURFACE INFORMATION (Roadway and Structures)1995-07
SP01 G115.docx
  
SP01GLOCATING EXISTING UNDERGROUND UTILITIES2012-03
SP01 G118.docx
  
SP01GRESOURCE CONSERVATION2013-05
SP01 G120.docx
  
SP01GDOMESTIC STEEL2013-04
SP01 G121.docx
  
SP01GPORTABLE CONC. BARRIER (Partial Payment for Mat's.)2011-08
SP01 G124.docx
  
SP01GREMOVABLE PVMT. MARKINGS (Partial Payment for Mat'l)2011-08
SP01 G125.docx
  
SP01GMAINTENANCE OF THE PROJECT2012-01
SP01 G133.docx
  
SP01GCOOPERATION BETWEEN CONTRACTORS1995-07
SP01 G142.docx
  
SP01GBID DOCUMENTATION2012-09
SP01 G145.docx
  
SP01GTWELVE-MONTH GUARANTEE2003-11
SP01 G146.docx
  
SP01GTWELVE-MONTH GUARANTEE (LGA ONLY)2013-12
SP01 G150.docx
  
SP01GOUTSOURCING OUTSIDE U.S.A.2006-05
SP01 G152.docx
  
SP01GGIFTS FROM VENDORS AND CONTRACTORS2009-12
SP01 G160.docx
  
SP01GLIABILITY INSURANCE2014-05
SP01 G180.docx
  
SP01GEROSION & STORM WATER CERTIFICATION2012-09
SP01 G181.docx
  
SP01GPROCEDURE FOR MONITORING BORROW PIT DISCHARGE2013-03
SP01 G182.docx
  
SP01GSUPPLEMENTAL CONTRACTOR EROSION CONTROL RESPONSIBILITIES (Rail)2013-02
SP01 G183.docx
  
SP01GSUPPLEMENTAL RESPONSE FOR EROSION CONTROL (Rail)2013-02
SP01 G184.docx
  
SP01GEMPLOYMENT2012-01
SP01 G185.docx
  
SP01GSTATE HIGHWAY ADMINISTRATOR TITLE CHANGE2012-09
SP01 G190.docx
  
SP01GREVISION TO FHWA-1273 CONCERNING TAP-FUNDED PROJECTS2013-10
SP01 G200.docx
  
SP01GE-VERIFY COMPLIANCE2014-02
SP01 R001.docx
  
SP01RPROJECT SPECIAL PROVISIONS (Roadway)1995-07
SP01 R004R.docx
  
SP01RSHOULDER CONSTRUCTION2012-08
SP01 R007AR.docx
  
SP01RSHOULDER RECONSTRUCTION (Stone, Seeding Separate)2012-08
SP01 R007BR.docx
  
SP01RSHOULDER RECONSTRUCTION (No Seeding & Mulching)2012-08
SP01 R007CR.docx
  
SP01RSHOULDER RECONSTRUCTION (No Stone, Seeding Separate)2013-11
SP01 R007DR.docx
  
SP01RSHOULDER RECONSTRUCTION (No Stone, No Seeding & Mulch)2012-08
SP01 R007ER.docx
  
SP01RSHOULDER RECONSTRUCTION (State Forces Seeding)2012-08
SP01 R007FR.docx
  
SP01RSHOULDER RECONSTRUCTION (Stone, Seeding Separate, Div 5)2012-08
SP01 R010AR.docx
  
SP01RSHOULDER CONSTRUCTION PROCEDURE2013-10
SP01 R010BR.docx
  
SP01RSHOULDER RECONSTRUCTION PROCEDURE2013-10
SP01 R034R.docx
  
SP01RCONSTRUCTION SEQUENCE2012-08
SP02 R002A.docx
  
SP02RCLEARING AND GRUBBING - Method II2012-01
SP02 R002B.docx
  
SP02RCLEARING AND GRUBBING - Method III2012-01
SP02 R005.docx
  
SP02RBURNING RESTRICTIONS1995-07
SP02 R010.docx
  
SP02RDEMOLISHION OF BUILDINGS AND APPURTENANCES2012-01
SP02 R015A.docx
  
SP02RBUILDING REMOVAL (Inside ROW)2013-04
SP02 R015B.docx
  
SP02RBUILDING REMOVAL (Cut Building at ROW)2013-04
SP02 R015C.docx
  
SP02RBUILDING REMOVAL (Both side of ROW)2013-04
SP02 R015D.docx
  
SP02RBUILDING AND UNDERGROUND STORAGE TANK REMOVAL2013-04
SP02 R016.docx
  
SP02RLUMP SUM GRADING2010-08
SP02 R030A.docx
  
SP02RTEMPORARY DETOURS (Lump Sum Grading)2013-11
SP02 R030B.docx
  
SP02RTEMPORARY DETOURS2013-11
SP02 R030C.docx
  
SP02RTEMPORARY DETOURS (Exception to Lump Sum Grading)2014-02
SP02 R045A.docx
  
SP02RSHOULDER AND FILL SLOPE MATERIAL (Lump Sum Grading)2012-01
SP02 R045B.docx
  
SP02RSHOULDER AND FILL SLOPE MATERIAL2012-01
SP02 R057.docx
  
SP02RBORROW EXCAVATION (Truck Measurement)1995-07
SP02 R058.docx
  
SP02RBORROW EXCAVATION (In Place or Truck Measurement)1995-07
SP02 R065.docx
  
SP02RSURCHARGES AND WAITING PERIODS2013-02
SP02 R075.docx
  
SP02REMBANKMENT SETTLEMENT GAUGES2013-02
SP02 R080.docx
  
SP02RSELECT GRANULAR MATERIAL2012-01
SP03 R001.docx
  
SP03RPIPE INSTALLATION2012-11
SP03 R005.docx
  
SP03RREINFORCED CONCRETE TAPERED INLET2012-11
SP03 R030.docx
  
SP03RFLOWABLE FILL2012-01
SP04 R002.docx
  
SP04RBRIDGE APPROACH FILLS2012-01
SP05 R005.docx
  
SP05RPREPARATION OF SUBGRADE AND BASE1996-01
SP05 R010.docx
  
SP05RAGGREGATE STABILIZATION2013-11
SP05 R020.docx
  
SP05RSOIL-CEMENT BASE (FULL DEPTH RECLAIMATION)2013-11
SP05 R028R.docx
  
SP05RINCIDENTAL STONE BASE2012-08
SP06 R001.docx
  
SP06RASPHALT PAVEMENTS SUPERPAVE 2014-02
SP06 R003R.docx
  
SP06RSHOULDER WEDGE2012-08
SP06 R006A.docx
  
SP06RASPHALT PAVER FIXED STRINGLINES2012-01
SP06 R006B.docx
  
SP06RASPHALT PAVER FIXED AND MOBILE STRINGLINES2012-01
SP06 R015.docx
  
SP06RASPHALT BINDER CONTENT OF ASPHALT PLANT MIX2012-07
SP06 R020.docx
  
SP06RASPHALT PLANT MIXTURES1995-07
SP06 R025.docx
  
SP06RPRICE ADJUSTMENT FOR ASPHALT BINDER FOR PLANT MIX2000-11
SP06 R045.docx
  
SP06RFINAL SURFACE TESTING NOT REQUIRED2012-05
SP06 R049R.docx
  
SP06RASPHALT CONCRETE SURFACE COURSE COMPACTION2012-08
SP06 R052R.docx
  
SP06RWEDGE COURSE2012-08
SP06 R056R.docx
  
SP06RWARRANTY OF ASPHALT SURFACE TREATMENT2012-08
SP06 R058R.docx
  
SP06RREPAIR OF EXISTING PAVEMENT2014-05
SP06 R061AR.docx
  
SP06RRESURFACING EXISTING BRIDGES2012-08
SP06 R061BR.docx
  
SP06RRESURFACING EXISTING BRIDGES (With Milling)2012-08
SP06 R062.docx
  
SP06ROPEN GRADED ASPHALT FRICTION COURSE, PERMEABLE ASPHALT DRAINAGE COURSE, AND ULTRA-THIN BONDED WEARING COURSE2012-04
SP06 R067AR.docx
  
SP06RPAVING INTERSECTIONS (State Forces)2012-08
SP06 R067BR.docx
  
SP06RPAVING INTERSECTIONS (Contractor Forces)2012-08
SP06 R070AR.docx
  
SP06RPAVING DRIVEWAYS AND MAILBOX TURNOUTS (State Forces)2012-08
SP06 R070BR.docx
  
SP06RPAVING DRIVEWAYS AND MAILBOX TURNOUTS (Contractor Forces)2012-08
SP06 R076R.docx
  
SP06RPAVEMENT WIDTH VARIES2012-08
SP06 R079AR.docx
  
SP06RTRENCHING FOR ASPHALT xxx COURSE (Base Course, Contractor Disposes of Excess)2012-08
SP06 R079BR.docx
  
SP06RTRENCHING FOR ASPHALT xxx COURSE (Int. Course, Contractor Disposes of Excess)2012-08
SP06 R082AR.docx
  
SP06RTRENCHING FOR ASPHALT xxx COURSE (Base Course, State Disposes of Excess)2012-08
SP06 R082BR.docx
  
SP06RTRENCHING FOR ASPHALT xxx COURSE (Int. Course, State Disposes of Excess)2012-08
SP06 R085R.docx
  
SP06RASPHALT CONC. SURF. COURSE, TYPE xxx (Leveling Course)2012-08
SP06 R088R.docx
  
SP06RPATCHING EXISTING PAVEMENT2012-12
SP08 R010.docx
  
SP08RMODIFIED CONCRETE FLUME WITH CONCRETE OUTLET2008-06
SP08 R015.docx
  
SP08RMODIFIED CONCRETE FLUME WITH FUNNEL OUTLET2006-07
SP08 R020.docx
  
SP08RSLUICE GATE2009-03
SP08 R045.docx
  
SP08RCONVERTING EXISTING DROP INLET TO SHOULDER DROP INLET2006-07
SP08 R050.docx
  
SP08RCONVERTING EXISTING ___ TO ___2006-07
SP08 R055.docx
  
SP08RREMOVAL AND STOCKPILE OF EXISTING GUARDRAIL2006-07
SP08 R060.docx
  
SP08RGUARDRAIL ANCHOR UNITS TYPE M-3502012-01
SP08 R064.docx
  
SP08RGUARDRAIL ANCHOR UNITS TYPE TL-22011-08
SP08 R065.docx
  
SP08RGUARDRAIL ANCHOR UNITS TYPE 3502011-08
SP08 R075.docx
  
SP08RIMPACT ATTENUATOR UNITS TYPE 3502012-01
SP08 R085.docx
  
SP08RTEMPORARY WOVEN WIRE FENCE2013-10
SP08 R095R.docx
  
SP08RADJUSTMENTS OF MANHOLES2012-08
SP08 R096R.docx
  
SP08RADJUSTMENTS TO MANHOLES2012-08
SP08 R097R.docx
  
SP08RADJUSTMENT OF MANHOLES, METER BOXES, AND VALVE BOXES2012-08
SP08 R100.docx
  
SP08RCHAIN LINK FENCE w/BARBED WIRE ON EXTENSION ARMS1995-07
SP08 R105.docx
  
SP08RPREFORMED SCOUR HOLE WITH LEVEL SPREADER2009-10
SP08 R125.docx
  
SP08RDETECTABLE WARNINGS FOR EXISTING CURB RAMPS2011-08
SP08 R126.docx
  
SP08RDETECTABLE WARNINGS FOR PROPOSED CURB RAMPS2011-08
SP08 R127.docx
  
SP08RREMOVE AND REPLACE CURB RAMPS2012-08
SP09 R002.docx
  
SP09RSTREET SIGNS AND ROUTE MARKERS1995-07
SP09 R005.docx
  
SP09RFOUNDATIONS AND ANCHOR ROD ASSEMBLIES FOR METAL POLES2013-05
SP10 R001.docx
  
SP10RMATERIALS2014-05
SP10 R002.docx
  
SP10RHIGH STRENGTH CONCRETE FOR DRIVEWAYS2012-01
SP10 R005.docx
  
SP10RSELECT MATERIAL, CLASS III, TYPE 32012-01
SP10 R010.docx
  
SP10RSHOULDER AND SLOPE BORROW2013-03
SP11 R002.docx
  
SP11RTEMPORARY SHORING2013-05
SP11 R005.docx
  
SP11RTEMPORARY TRAFFIC CONTROL DEVICES2012-01
SP11 R010.docx
  
SP11RTRUCK MOUNTED CHANGEABLE MESSAGE SIGNS2012-08
SP14 R002.docx
  
SP14RCOORDINATION OF LIGHTING WORK2012-08
SP15 R020.docx
  
SP15RSANITARY SEWER2013-11
SP16 R002.docx
  
SP16RPERMANENT SEEDING AND MULCHING1995-07
SP16 R003R.docx
  
SP16REROSION AND STORMWATER CONTROL FOR SHOULDER2012-08
T S1East.doc
  
TSEED MIX EAST (Alamance, Anson, Franklin, Guilford, Orange, Person, Vance, Wake and Warren)2011-11
T S2.doc
  
TSEED MIX EAST CRIMP (All other counties not listed elsewhere)2011-11
T S2A.doc
  
TSEED MIX DIVISION 3 CRIMP (Brunswick, Duplin, New Hanover, Onslow, Pender, and Sampson)2011-11
T S3.doc
  
TSEED MIX WEST (Alexander, Alleghany, Ashe, Avery, Cabarrus, Caldwell, Caswell, Catawba, Cleveland, Davidson, Davie, Forsyth, Gaston, Iredell, Lincoln, Mechlenburg, Rockingham, Rowan, Stanly, Stokes, Surry, Union, Watauga, Wilkes, and Yadkin)2011-11
T S4.doc
  
TSEED MIX WEST ED (Buncombe, Burke, Cherokee, Clay, Graham, Haywood, Henderson, Jackson, Macon, Madison, Mitchell, Polk, Rutherford, Swain, Transylvania, and Yancey)2011-11
T1.docx
  
TWATTLES2012-01
T2.docx
  
TWATTLES WITH POLYACRYLAMIDE (PAM)2012-01
U RWZ1.docx
  
UWORK ZONE TRAFFIC CONTROL GENERAL REQUIREMENTS2014-02
Z001.docx
  
ZPERMITS COVER (Delete Not Applicable Information)2014-02
Z001A.docx
  
ZPERMIT COVER (No Additional Permits)2014-02
Z002.docx
  
ZAVAILABILITY OF FUNDS2008-05
Z003.docx
  
ZSEED QUALITY (Do NOT use if seeding is NOT required on project)2011-05
Z004.docx
  
ZERRATA2014-01
Z004A.docx
  
ZPLANT PEST QUARANTINE2013-10
Z005.docx
  
ZMINIMUM WAGE (State Funded)2009-07
Z006.docx
  
ZAWARD OF CONTRACT1977-06
Z007.docx
  
ZMINORITY AND FEMALE EMPLOYMENT (Prime Contractor Company wide)2000-00
Z008.docx
  
ZFHWA 12732012-05
Z009.docx
  
ZFHWA 1273, Attachment A (Appalachian Only), add to Z-81994-10
Z010.docx
  
ZOn the Job Training - USE ON ALL PROJECTS2013-05
Z086.docx
  
ZDAVIS-BACON DECISIONS - Beaufort, Dare, Pamlico, Bertie, Gates, Pasquotank, Camden, Hertford, Perquimans, Carteret, Hyde, Tyrrell,Chowan, Jones, Washington, Craven, Martin2014-02
Z087.docx
  
ZDAVIS-BACON DECISIONS - Cumberland, Currituck, Hoke , Onslow2014-02
Z088.docx
  
ZDAVIS-BACON DECISIONS - Buncombe, Haywood, Henderson, Madison2014-02
Z089.docx
  
ZDAVIS-BACON DECISIONS - Alexander, Burke, Caldwell, Catawba2014-02
1 - 200Next
 

 2012 Standard Specifications

 
 

 Resources

 
 

 Additional Provisions

 
Was this page helpful?