• 02 EARTHWORK

  • SECTION 260 PROOF ROLLING

  •  
     


    260-1 DESCRIPTION
     
    The Contractor may operate the proof roller at times other than when directed by the Technician. Such use is at the Contractor’s election and is not to be considered as work performed under this section.
     
    The requirement for proof rolling, when required by the contract, may not be eliminated or modified without written approval.

    260-2 EQUIPMENT
     
    The Engineer and Technician shall check to see that the equipment conforms to the requirements of this article, observe ballast loading, and check tire pressure each time the equipment is used. In order not to trap water, thereby increasing the weight, the roller should be covered with suitable material to prevent intrusion of water.
     
    Weight tickets signed by a licensed public weighmaster may be used to determine the empty weight of the roller and the weight of bulk ballast to be used.
     
    Requests by the Contractor to substitute other types of equipment shall be forwarded to the State Construction Engineer through the Division Engineer for approval or disapproval.
     
    The Contractor shall not be permitted to tow the loaded proof roller over existing structures or pavement. Refer to Article 105-15 of the Specifications and this Manual.

    260-3 CONSTRUCTION METHODS
     
    Proof rolling is to be done when the roadbed is within plus or minus 6 inches of finished grade and the roadbed shall be rolled for a width located between points 2 feet outside the proposed edges of pavement including shoulder pavement. Care should be taken when operating over drainage that is within 6 feet of subgrade. The Contractor should construct ramps to prevent crushing top drainage pipes. If damage is suspected, the Materials and Tests Unit ​can perform a camera investigation.
     
    A coverage is considered to be that stage in the rolling procedure when the entire area to be proof rolled has been covered by the body of the proof roller. Complete coverage will not include the area between the pneumatic tires. Each additional pass should overlap the previous pass by a minimum of 1 tire width.
     
    Areas which have failed and been repaired shall be proof rolled again to confirm stability.
     
    The Technician shall follow the proof roller observing the action of the roadbed produced immediately behind the tires of the roller. When the roadbed material compresses and remains compressed, the roadbed is satisfactory. When the roadbed material compresses and then rebounds to any appreciable extent, further testing and investigation and consultation with the Engineer and/or the Geotechnical Unit ​shall be made. Horizontal slippage or crust breakage is not considered as failure.
     
    The Engineer and Technician shall take immediate steps to determine the cause of any failures observed. Failures are typically caused by unsuitable materials or excessively wet materials. These conditions may be found to be as much as 6 feet below the roadbed surface. Assistance in determining corrective action required may be obtained from the Geotechnical Unit.
     
    Should it be determined that the failure is due to negligence or is not compensable under the Specifications, the Engineer shall so inform the Contractor in writing.

    260-4 MEASUREMENT AND PAYMENT
     
    No measurement of rolling time is to be made when:
     
    1. The roller is being used for the Contractor’s convenience.  
       
    2. The Technician is not present.  
       
    3. Rolling is necessary due to corrective action made necessary by the negligence of the Contractor or damage from weather.

    ADDITIONAL RESOURCES
No content found
No content found
No content found
No content found

Materials

No content found

Measurement and Payment

‭(Hidden)‬ Related Documents

No content found
Was this page helpful?